DevFeeFinder
UtilitiesSet by city fee ordinance

General City DIF - Solid Waste

Levied by City of Ontario on new development in Ontario. Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. Collected at building permit.

What one house pays

$773

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot — this fee varies by the row that applies, so see the full schedule below.

Share of Ontario's total
1%
Total one-time fees here
$56,975
Adjustment
Adjusts only when the board sets a new amount
what the document says

by resolution of the City Council; no interim escalator - Res. No. 2025-010 adopts two dated schedules and names no index

The record

Why it exists

“This chapter contains a calculation of the demand from development upon the City's inventory of refuse collection equipment, storage and maintenance facilities. The existing refuse capacity is the result of existing customer rate and fee payments. The inventory is also needed to serve the existing inventory of residential and business space. New refuse customers will impact the City by requiring new refuse vehicles and various types of collection containers which in turn will increase demand upon the refuse collection system facilities and maintenance capacity.”

Development Impact Fee Calculation and Nexus Report, City of Ontario 21-22 Update, adopted 2022-07-15, Chapter 9 "Refuse Collection Facilities and Equipment", printed page 119 / PDF page 124, opening paragraph · source document ↗
What it pays for

“RS-001 Side Loader Collection Barrels 2040 / RS-002 Side Loader Collection Vehicles 2035 / RS-003 Front Loader Collection Bins 2040 / RS-004 Front Loader Collection Vehicles 2035 / RS-005 Roll-Off Collection Bins 2040 / RS-006 Roll-Off Collection Vehicles 2035 / RS-007 Share of Specific/Common City Yard Improvements 2045 / RS-008 Fund Balance Refuse Acquisition”

City of Ontario 2024-25 Master Facilities Plan, Estimated Project Completion Date appendix, "Project # / Project Title / Estimated Completion Date", printed page 513 / PDF page 530, RS block · source document ↗
Where it applies

“In 2000 the City of Ontario retained Revenue & Cost Specialists to undertake a comprehensive cost calculation of the City's development impact costs for two areas of the City. The two areas consisted of the more developed General City (GC) area and the largely undeveloped former dairy farm area referred to as Ontario Ranch (OR). Ontario Ranch had been referred to as New Model Colony in previous reports but it was amended to Ontario Ranch in this 2017 update at the request of the Ontario Ranch Builders.”

Development Impact Fee Calculation and Nexus Report, 21-22 Update, Chapter 1 "Background and Introduction", printed page 1 / PDF page 6 · source document ↗
When it was adopted

2003-07-01

“On July 1, 2003, the City Council adopted Ordinance Nos. 2779 and 2780 approving the collection of Development Impact Fees (DIF) in the City of Ontario to mitigate the impacts of future development. In accordance with the provisions of Ordinance Nos. 2779 and 2780, the City began collecting DIF on September 1, 2003.”

AB 1600 Development Impact Fee Annual Report (Unaudited), For Fiscal Year Ended June 30, 2025, "AB 1600 Development Impact Fee Annual Report – Introduction", page 1 of 19 · source document ↗
Who adopted it

Ordinance Nos. 2779 and 2780

“On July 1, 2003, the City Council adopted Ordinance Nos. 2779 and 2780 approving the collection of Development Impact Fees (DIF) in the City of Ontario to mitigate the impacts of future development. In accordance with the provisions of Ordinance Nos. 2779 and 2780, the City began collecting DIF on September 1, 2003.”

AB 1600 Development Impact Fee Annual Report (Unaudited), For Fiscal Year Ended June 30, 2025, "AB 1600 Development Impact Fee Annual Report – Introduction", page 1 of 19 · source document ↗
When it is paid

at building permit

“GENERAL CITY (GC) DEVELOPMENT IMPACT FEES EFFECTIVE 07/01/2026 / COLLECTED AT BUILDING PERMIT ($)”

General City (GC) Development Impact Fees Effective as of July 1, 2026, sheet heading; footer "CC Resolution No. 2025-010 (Effective 07/01/26)" · source document ↗
Who collects it

City of Ontario, the agency that levies it

“The City of Ontario assesses certain Development Impact Fees (DIF) upon new development projects to recover the costs to the City for the future construction of public infrastructure, facilities, and improvements necessitated by increased development. DIF are collected at Building Permit issuance to ensure the City collects sufficient monies to construct the additional infrastructure needed to accommodate the growth of new residents and businesses.”

City of Ontario, "Development Impact Fees" page, opening paragraph · source document ↗
Credits and offsets

“Developers shall submit a "DIF Credit Request" or "DIF Reimbursement Request" in order to receive DIF Credit or DIF Reimbursement, for the construction and completion of DIF Program infrastructure included in the City's DIF Nexus Report. When an improvement is complete, Developer shall submit a request to the City with all supporting documentation to DIF@ontarioca.gov.”

City of Ontario, "DIF Credit or Reimbursement Requests" page · source document ↗
How it changes

“SECTION 5. This Resolution, including the updated fee amounts contained in "Exhibit A" and "Exhibit B" attached hereto and incorporated herein, shall be effective for all new development projects occurring in the City, when applicable, sixty (60) days following its adoption.”

Resolution No. 2025-010, adopted 2025-03-18, Section 5, page 3 of 5 · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
General City
Single-family detached detached dwellingthis home per DU 1 Jul 2026 $773.00

“General City - Maximum Solid Waste Collection Development Impact Fees by Land Use — Proposed Land Use | Impact Fee per Unit or S.F. — Detached Dwellings | $ 773/Unit”

Resolution No. 2025-010, adopted 2025-03-18, "EXHIBIT B" — City of Ontario Development Impact Fee Schedule 07.01.26, PDF page 22 · source document ↗
Single-family attached attached dwelling per DU — $657.00
the line this rate was read from

“General City - Maximum Solid Waste Collection Development Impact Fees by Land Use — Attached Dwellings | $ 657/Unit”

the levying document · source document ↗
Mobile home mobile home dwelling per DU — $657.00
the line this rate was read from

“General City - Maximum Solid Waste Collection Development Impact Fees by Land Use — Mobile Home Dwellings | $ 657/Unit”

the levying document · source document ↗
Multi-family high density dwelling per DU — $329.00
the line this rate was read from

“General City - Maximum Solid Waste Collection Development Impact Fees by Land Use — High Density Dwellings | $ 329/Unit”

the levying document · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close