School Facilities Fee (Level 1) - Kern High SD

Levied by Kern High School District on new development in Shafter. Authorized under the Ed. Code Sec. 17620; Gov. Code Sec. 65995 et seq. (statutory school facilities fee). Collected at building permit.

What one house pays

$3,760

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Shafter's total
12%
Total one-time fees here
$31,067
Adjustment
Adjusts only when the board sets a new amount
what the document says

by resolution — the Board re-adopts an increased fee by resolution after a public hearing; no document found states an automatic index or annual adjustment for KHSD's own fee

Next expected change
1 Jul 2027 rate on file is stale
!

A scheduled adjustment has passed since this rate took effect

This fee escalates annually. The rate on file is effective 7 Apr 2026, and at least one adjustment has fallen due since. The current amount is probably different, and for an indexed fee almost certainly higher. The next change after that is expected 1 Jul 2027.

The figure is published as held rather than projected forward, because a number computed from an index is not a number quoted from an adopted schedule. It is flagged so you can check the agency's current schedule before relying on it.

The record

Why it exists

“Developer Fees collected by the District will be used for the construction and/or acquisition of land and school facilities necessary to accommodate students from new development, including additional classrooms, Career Technical Education facilities, and installation of portable classrooms.”

KHSD "Developer Impact Fee Annual and Five-Year Report for the Fiscal Year Ending June 30, 2025", November 10, 2025, s. II.A "Purpose of Fees (§ 66001(d)(1)(A))" · source document ↗
What it pays for

“The Developer Fees collected by the District consist of: - Statutory School Facilities Fees (Level 1 Fees) authorized under Education Code § 17620 and Government Code §§ 65995 et seq. - Alternative School Facilities Fees (Levels 2 and 3) authorized under Government Code §§ 65995.5, 65995.6, and 65995.7. These fees are imposed on new residential, commercial, and industrial construction within the District's boundaries to fund school facilities required to serve students generated by that development.”

KHSD Developer Impact Fee Annual and Five-Year Report FYE June 30, 2025, November 10, 2025, s. I.A "Description of Fee Type" · source document ↗
Where it applies

“The District provides education to students in grades Transitional Kindergarten ("TK") through 8 residing within a portion of the City of Shafter ("City") and a portion of the unincorporated area of the County of Kern ("County"). ... The District is required to share a portion of the maximum School Fee with Kern Union High School District, as a result the District can only collect 65 percent, or $3.50 per square foot, for all new Future Units built within its boundaries.”

Richland School District, "School Facilities Fee Justification Report", June 22, 2026, s. II "The School District", p.3 and s. V.A "Maximum Residential School Fee", p.14 · source document ↗
When it is paid

at building permit

“Fees and exactions required of a development pay for public facilities associated with a residential development. The City of Shafter charges two types of fees: development impact fees and planning processing fees. Planning-related fees are collected at time of project application submittal; development impact fees are collected at the time of building permit issuance and are primarily assessed based upon a per unit/lot basis.”

Shafter 2023-2031 Housing Element, January 2024, Chapter IV Constraints, "Fees and Exactions", printed p.167 — page footer reads "Draft" · source document ↗
Who collects it

“An approved site plan is sent to the Building Division after corrections are submitted and approved, fees are collected and verification of payment of school fees, development impact fees per Ordinance, utility connections; the Building Division then issues construction permit upon payment of permit fees”

Shafter 2023-2031 Housing Element, January 2024, Chapter IV, "Single-Family Dwellings" procedure list, printed p.163 — page footer reads "Draft" · source document ↗
Who is exempt

“The Richland School District exempts housing for seniors (ages 55 or older) from paying school impact fees.”

Shafter 2023-2031 Housing Element, January 2024, Chapter IV, "Development Impact Fees", printed p.167 — this is the ELEMENTARY district's exemption; no KHSD senior exemption was found · source document ↗

Every published rate

Every rate below applies to residential.

RateBasisEffectiveAmount
Kern High SD
this homeunverified per sq ft 7 Apr 2026 $1.88

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close