DevFeeFinder
ParksSet by city fee ordinance

Park in-lieu fee (acquisition and improvements)

Levied by City of Shafter on new development in Shafter. Collected other: at such time as established by the conditions of approval for the project; may be required prior to approval of the final map — the City's Housing Element separately says impact fees are collected at building permit issuance (conflict).

What one house pays

$2,281

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Shafter's total
7%
Total one-time fees here
$31,067
Adjustment
Adjusts only when the board sets a new amount
what the document says

by resolution — the Development Code sets the fee "by resolution of the City Council" and names no index

The record

Why it exists

“10.200 PARK AND RECREATION FACILITIES — The City may, as established by the Open Space and Conservation Element of the General Plan and this Title, require, as a condition of approval for development projects, the payment of fees and/or dedication of land for the provision of neighborhood or community parks and/or recreational facilities. The General Plan establishes the ultimate proportion of 2.5 acres of neighborhood park, community park, and recreational facilities per 1,000 persons residing in the City.”

City of Shafter Development Code, Chapter 10 General Development Standards, s. 10.200, printed p. 10-32 · source document ↗
What it pays for

“(b) Whenever fees are paid pursuant to this Section, the City shall deposit them into a separate park fund. All fees paid may be used only for the purpose of developing new or rehabilitating existing neighborhood or community park or recreational facilities to serve the subdivision. The development of new park and recreational facilities includes, but is not limited to, the acquisition of land for neighborhood or community parks for recreational purposes. Fees shall be expended for use only within the boundaries of the City.”

City of Shafter Development Code, s. 10.200.4.e(8)(b), printed p. 10-35 · source document ↗
Where it applies

“Fees shall be expended for use only within the boundaries of the City.”

City of Shafter Development Code, s. 10.200.4.e(8)(b), printed p. 10-35 · source document ↗
When it was adopted

1996-05-28 (Title 17 as published; no section-level history for §10.200)

“CITY OF SHAFTER MUNICIPAL CODE TITLE 17 ZONING ORDINANCE (ORDINANCE NO. 472) CITY OF SHAFTER 336 PACIFIC AVENUE SHAFTER, CA 93263 May 28, 1996 (Updated 03/20/26)”

City of Shafter Development Code, cover page, edition updated 03/20/26 · source document ↗
Who adopted it

Ordinance No. 472 (City of Shafter Municipal Code Title 17, Zoning Ordinance / Development Code)

“CITY OF SHAFTER MUNICIPAL CODE TITLE 17 ZONING ORDINANCE (ORDINANCE NO. 472) CITY OF SHAFTER 336 PACIFIC AVENUE SHAFTER, CA 93263 May 28, 1996 (Updated 03/20/26)”

City of Shafter Development Code, cover page, edition updated 03/20/26 · source document ↗
When it is paid

“f. When required, fees shall be paid at such time as established by conditions of approval for a project. Payment may be required prior to approval of a final map if the fees are to reimburse the City for expenditures previously made or for an account which has been established wherein the City has adopted a proposed construction schedule or plan.”

City of Shafter Development Code, s. 10.200.3.f, printed p. 10-33 · source document ↗
Who collects it

City of Shafter, the agency that levies it

“An approved site plan is sent to the Building Division after corrections are submitted and approved, fees are collected and verification of payment of school fees, development impact fees per Ordinance, utility connections; the Building Division then issues construction permit upon payment of permit fees”

Shafter 2023-2031 Housing Element, January 2024, Chapter IV Constraints, "Single-Family Dwellings", printed p. 163 · source document ↗
Who is exempt

“2. Exemptions — This Section shall not apply to the following subdivisions: a. Commercial or industrial developments. b. Condominium projects or stock cooperatives, which consist of the subdivision of air space in an existing apartment building that is more than five years old and in which no new dwelling units have been added by the subdivision. c. Subdivisions containing less than five parcels and not used for residential purposes, provided, however, that a condition of approval shall be placed on those maps stating that if a building permit is requested for the construction of a residential structure or structures on one or more of the parcels within four (4) years after recordation of the subdivision map, the fees shall be paid by the owner of each parcel as a condition to the issuance of such permit.”

City of Shafter Development Code, s. 10.200.2, printed p. 10-32 · source document ↗
Credits and offsets

“(c) The subdivider or developer may receive a credit against fees as follows: 1) A credit may be given against the requirements for the payment of fees or the dedication of land required by this subsection for the reasonable value of park and recreation improvements provided by the subdivider or developer, if approved and accepted by the City. The amount of the credit shall be determined prior to the approval or conditional approval of a tentative map or equivalent for other residential projects not involving a subdivision.”

City of Shafter Development Code, s. 10.200.4.e(8)(c), printed p. 10-35 · source document ↗

Every published rate

Every rate below applies to single-family detached.

RateBasisEffectiveAmount
this homeunverified per DU — $2,281

“Table IV-4 Development Impact Fees | FEE | COST | PER | ... | Park Fees | a. In-lieu fee (acquisition and improvements) | $2281 | Dwelling Unit”

Shafter 2023-2031 Housing Element, January 2024, Chapter IV Constraints, Table IV-4, printed p. 168 · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close