Levied by City of San Jacinto on new development in San Jacinto. Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. Collected other: "Payable prior to final inspection" per the adopted fee schedule — which CONFLICTS with the City's own AB 1600 report, which says DIFs are collected at building permit issuance.

What one house pays

$212

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of San Jacinto's total
0%
Total one-time fees here
$58,741
Adjustment
Does not adjust
what the document says

none - the schedule states no adjustment clause

The record

Why it exists

“DIFs are charged by local governmental agencies in connection with approval of development projects. The purpose of these fees is to defray all or a portion of the cost of public facilities related to the development project.”

FY 2022-23 Development Impact Fee Report, Letter of Transmittal, December 19, 2023, p. 1 · source document ↗
What it pays for

“FY 2022/23 Project Expenditures / Fire Engine $150,746”

FY 2022-23 Development Impact Fee Report, "Public Safety Facility Development Funds", report p. 9 · source document ↗
Where it applies

“CITY OF SAN JACINTO Development Fee Schedule / Rev: 07/01/2026 | Fee Type | Single Family Residential | Multi Family Res (Apt) | Retail Commercial | Non-Retail Comm / Ind | Comments”

City of San Jacinto Development Fee Schedule, Rev: 07/01/2026, title and column-header row — the sheet is citywide and names no benefit area, sub-area or district · source document ↗
When it was adopted

2005-05-19

“Fire Development Impact Fund (116) – Per Ordinance 05-18, May 19, 2005 added a development impact fee for additional fire facilities and additional fire vehicles needed as a result of new development, and population growth.”

City of San Jacinto Fiscal Year 2022-23 Development Impact Fee Report, transmitted December 19, 2023, "DEVELOPMENT IMPACT FUNDS" / "Public Safety Facility Development Funds", report p. 3 · source document ↗
Who adopted it

"Ordinance 05-18"

“Fire Development Impact Fund (116) – Per Ordinance 05-18, May 19, 2005 added a development impact fee for additional fire facilities and additional fire vehicles needed as a result of new development, and population growth.”

City of San Jacinto Fiscal Year 2022-23 Development Impact Fee Report, transmitted December 19, 2023, "DEVELOPMENT IMPACT FUNDS" / "Public Safety Facility Development Funds", report p. 3 · source document ↗
When it is paid

“Fire Facilities $212.00/dwelling unit ... Payable prior to final inspection”

City of San Jacinto Development Fee Schedule, Rev: 07/01/2026, "Public Safety Facilities" group, Fire Facilities row, "Comments" column · source document ↗
Who collects it

City of San Jacinto, the agency that levies it

“In San Jacinto, DIFs are collected at the time a building permit is issued for the purpose of mitigating the impacts caused by new development on the City's infrastructure. Fees are used to finance the acquisition, construction and improvement of public facilities needed as a result of this new development.”

FY 2022-23 Development Impact Fee Report, Letter of Transmittal, December 19, 2023, p. 1 · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
—
Single-family detached this home per DU 1 Jul 2026 $212.00

“Fire Facilities $212.00/dwelling unit”

City of San Jacinto Development Fee Schedule, Rev: 07/01/2026; read across from the "Fee Type" label "Fire Facilities", under the sub-heading "Public Safety Facilities", the amount sits in the column headed "Single Family Residential"; "Comments" column reads "Payable prior to final inspection" · source document ↗
none
Multi-family none per DU — $179.00
the line this rate was read from

“Fire Facilities ... $179.00/dwelling unit" under the column heading "Multi Family Res (Apt)”

the levying document · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close