DevFeeFinder
HabitatSet by habitat plan feeCitation Rancho Cordova Municipal Code ch. 22.45 (Ord. 24-2018 s. 4 (Exh. A))

SSHCP Mitigation Fee

Levied by City of Rancho Cordova (Rancho Cordova Municipal Code ch. 22.45) on new development in Rancho Cordova. Authorized under the Article XI, Section 7 of the California Constitution. NOT the Mitigation Fee Act, which the chapter invokes only for accounting. Collected other: before issuance of any permit for a development project; assessed one time per lot or parcel.

What one house pays

$3,047

This fee is not in Rancho Cordova's published figure. This site publishes a home outside any plan area, and this charge applies only in SSHCP plan area (south of U.S. Highway 50). The amount shown is what it costs a house that is there.

Total one-time fees here
$94,316
Adjustment
Adjusts yearly · ENR construction cost index
what the document says

annual - Home Price Index for land acquisition, California Construction Cost Index for all other costs

Next expected change
1 Jul 2027 rate on file is stale
!

A scheduled adjustment has passed since this rate took effect

This fee escalates annually. The rate on file is effective 15 Nov 2025, and at least one adjustment has fallen due since. The current amount is probably different, and for an indexed fee almost certainly higher. The next change after that is expected 1 Jul 2027.

The figure is published as held rather than projected forward, because a number computed from an index is not a number quoted from an adopted schedule. It is flagged so you can check the agency's current schedule before relying on it.

The record

Why it exists

“The preservation of vegetation communities and natural areas within the southern portion of Sacramento County which support species covered by the South Sacramento Habitat Conservation Plan (SSHCP) is necessary to protect and promote the health, safety and welfare of all the citizens of the County by reducing the adverse direct, indirect and cumulative effects of urbanization and development and providing for permanent conservation of habitat for species covered by the SSHCP.”

Sacramento County Code § 22.45.010.A Findings, SCC 1628 §1, 2018; SCC 1757, 7/22/2025 · source document ↗
What it pays for

“The fees collected pursuant to this Ordinance shall be used to finance the acquisition of the natural ecosystems and certain improvements described or identified in the SSHCP.”

Sacramento County Code § 22.45.010.J Findings · source document ↗
Where it applies

“The South Sacramento Conservation Agency (SSCA) is hereby appointed as the administrator of this chapter. SSCA is hereby authorized to receive all fees generated from the SSHCP mitigation fee within the city, and to invest, account for and expend such fees in accordance with the provisions of this chapter and the Mitigation Fee Act.”

Rancho Cordova Municipal Code ch. 22.45, "Establishment of Mitigation Fees for the South Sacramento Habitat Conservation Plan", s. 22.45.020 Administrative responsibility; ordinance history "(Ord. 24-2018 §4 (Exh. A))" · source document ↗
When it was adopted

2018

“(SCC 1628 §1, 2018; SCC 1757, 7/22/2025)”

Sacramento County Code Ch. 22.45 "SSHCP MITIGATION FEE", history note printed after every section of the chapter, incl. §§ 22.45.010, .020, .040, .050, .060, .070, .080, .090, .100 · source document ↗
Who adopted it

Rancho Cordova Municipal Code ch. 22.45 (Ord. 24-2018 s. 4 (Exh. A))

“The South Sacramento Conservation Agency (SSCA) is hereby appointed as the Administrator of this chapter. SSCA is hereby authorized to receive all fees generated from the SSHCP mitigation fee within the city, and to invest, account for and expend such fees in accordance with the provisions of this chapter and the Mitigation Fee Act.”

Rancho Cordova Municipal Code Title 22, Chapter 22.45 "ESTABLISHMENT OF MITIGATION FEES FOR THE SOUTH SACRAMENTO HABITAT CONSERVATION PLAN", ss. 22.45.010-22.45.100 (Ord. 24-2018 s. 4 (Exh. A)). Read 2026-09-10 in a browser at ecode360.com. · source document ↗
When it is paid

other: before issuance of any permit for a development project; assessed one time per lot or parcel

“Notwithstanding any other provision of this code, no permit shall be issued for any development project unless the SSHCP mitigation fee applicable to such development project has been paid.”

Rancho Cordova Municipal Code s. 22.45.050 Imposition of the SSHCP mitigation fee · source document ↗
Who collects it

“Subject to the provisions of this section, all fees collected pursuant to this chapter shall be remitted to the South Sacramento Conservation Agency at least quarterly.”

Rancho Cordova Municipal Code s. 22.45.080(B) Accounting and disbursement of collected SSHCP mitigation fees · source document ↗
Who is exempt

“Reconstruction or improvements that are damaged or destroyed by fire or other natural causes, provided that the reconstruction or improvements do not result in additional usable square footage." ... "Rehabilitation or remodeling to an existing Development Project, provided that the rehabilitation or remodeling do not result in additional usable square footage." ... "Accessory Dwelling Units, constructed on developed residential property and meeting all state and County requirements for such units.”

Sacramento County Code § 22.45.090 Exemptions, subsections A, B and C · source document ↗
Credits and offsets

“When the dedication of land is accepted into the SSHCP Preserve System, the SSHCP Mitigation Fee will be adjusted by excluding the appropriate portion of the land acquisition component”

Sacramento County Code § 22.45.100 Land Dedication in Lieu of Development Fees · source document ↗

Every published rate

Applies toBasisEffectiveAmount
Vernal Pool - direct per acre 15 Nov 2025 $294,496
the line this rate was read from

“Vernal Pool - Direct $294,496" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Mine Tailing Riparian Woodland per acre 15 Nov 2025 $219,055
the line this rate was read from

“Mine Tailing Riparian Woodland $219,055" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Streams/Creeks (VPIH) - direct per acre 15 Nov 2025 $218,404
the line this rate was read from

“Streams/Creeks (VPIH) - Direct $218,404" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Riparian per acre 15 Nov 2025 $216,238
the line this rate was read from

“Riparian $216,238" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Freshwater Marsh per acre 15 Nov 2025 $212,139
the line this rate was read from

“Freshwater Marsh $212,139" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Seasonal Wetland per acre 15 Nov 2025 $211,214
the line this rate was read from

“Seasonal Wetland $211,214" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Swale - direct per acre 15 Nov 2025 $198,288
the line this rate was read from

“Swale - Direct $198,288" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Streams/Creeks per acre 15 Nov 2025 $182,252
the line this rate was read from

“Streams/Creeks $182,252" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Blue Oak per acre 15 Nov 2025 $180,559
the line this rate was read from

“Blue Oak $180,559" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Open Water per acre 15 Nov 2025 $171,719
the line this rate was read from

“Open Water $171,719" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Streams/Creeks (VPIH) - indirect per acre 15 Nov 2025 $56,927
the line this rate was read from

“Streams/Creeks (VPIH) - Indirect $56,927" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Vernal Pool - indirect per acre 15 Nov 2025 $47,832
the line this rate was read from

“Vernal Pool - Indirect $47,832" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Swale - indirect per acre 15 Nov 2025 $27,795
the line this rate was read from

“Swale - Indirect $27,795" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Valley Grassland per acre 15 Nov 2025 $25,466
the line this rate was read from

“Valley Grassland $25,466" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗
Agriculture (cropland/irrigated pasture) (assumes prior cover: agricultural cropland) per acre 15 Nov 2025 $23,441
the line this rate was read from

“Agriculture (Cropland and Irrigated Pastureland) $23,441" under the column heading "Fee per acre (2025)*”

2025 SSHCP Mitigation Fee Schedule, "*These fees will go into effect on November 15, 2025" · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close