Sewer - treatmentSet by special district feeCitation M1W Ordinance No. 2021-02, para. 3

Monterey One Water residential sewer capacity charge

Levied by Monterey One Water on new development in Marina. Authorized under the Gov. Code Sec. 66013 where the charge is for water or sewer capacity; otherwise the district's own enabling act (Health & Safety Code / Pub. Resources Code, by district type). Collected other: at application for the M1W sewer capacity (connection) permit, which must be obtained before the city or district issues the building permit.

What one house pays

$6,094

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Marina's total
11%
Total one-time fees here
$54,020
Adjustment
Adjusts yearly · ENR construction cost index · July
what the document says

ENR CCI San Francisco, December index, annual

Next expected change
1 Jul 2027 rate on file is stale
!

A scheduled adjustment has passed since this rate took effect

This fee escalates annually. The rate on file is effective 1 Jul 2024, and at least one adjustment has fallen due since. The current amount is probably different, and for an indexed fee almost certainly higher. The next change after that is expected 1 Jul 2027.

The figure is published as held rather than projected forward, because a number computed from an index is not a number quoted from an adopted schedule. It is flagged so you can check the agency's current schedule before relying on it.

The record

Why it exists

“The sewer capacity charge is a fee assessed for all new or increased connections to cover a portion of the capital costs related to wastewater transmission, treatment, and disposal.”

"SEWER CAPACITY CHARGES PURSUANT TO AGENCY ORDINANCES / EFFECTIVE JULY 1, 2023 / RESIDENTIAL", p. 1, opening paragraph · source document ↗
What it pays for

“This charge helps to cover costs related to providing and maintaining excess capacity currently available within the Regional System.”

"SEWER CAPACITY CHARGES PURSUANT TO AGENCY ORDINANCES … RESIDENTIAL", effective July 1 2023, p. 1 · source document ↗
Where it applies

“Pursuant to the provisions of Article 5, Sections 5.01 through 5.05 of M1W Ordinance No. 79-2, and as amended by M1W Ordinance No. 81-1, thereby is hereby established and levied upon all persons, firms, or corporations making connections to a community sewer system within the M1W, a sewer capacity charge.”

Ordinance No. 2021-02, adopted 2021-11-29, Paragraph 3 "Capacity Charges", p. 10 · source document ↗
When it was adopted

2021-11-29

“This Ordinance No. 2021-02 was passed and adopted by a vote of not less than two-thirds of the Board of Directors of Monterey One Water at a regular meeting of the Board held on November 29, 2021”

Codified Version of Ordinance Nos. 2001-01 … 2020-01 and 2021-01; Ordinance No. 2021-02, adopted 2021-11-29, p. 14, signature block · source document ↗
Who adopted it

Ordinance No. 2021-02

“This Ordinance No. 2021-02 was passed and adopted by a vote of not less than two-thirds of the Board of Directors of Monterey One Water at a regular meeting of the Board held on November 29, 2021”

Codified Version of Ordinance Nos. 2001-01 … 2020-01 and 2021-01; Ordinance No. 2021-02, adopted 2021-11-29, p. 14, signature block · source document ↗
When it is paid

“The Amount Due shown above must be paid prior to being issued a building permit by your city or district.”

"MARINA RESIDENTIAL SEWER CAPACITY CHARGE DETERMINATION / 2024-2025", NEW FACILITIES RESIDENTIAL block · source document ↗
Who collects it

Monterey One Water, the agency that levies it

“The capacity charge described above is collected by Monterey One Water. Please check with the city in which you are looking to build or expand your usage to determine if additional capacity fees are assessed by your city, in addition to those assessed by M1W.”

Monterey One Water, "Residential Capacity Charges", page body, bolded paragraph beneath the rate table · source document ↗
Who is exempt

“Buildings or occupied mobile home pads which were connected to the community sewer of entity being serviced by the M1W at the time said entity was annexed to the M1W shall be exempt from these sewer capacity charges to the extent of their existing use and EDUs at such time of annexation.”

Ordinance No. 2021-02, adopted 2021-11-29, Paragraph 3.D "Demolished Premises" / "Existing Premises", p. 11 · source document ↗
Credits and offsets

“Credit for demolition will be given using the charge in effect at the time of payment. Only buildings demolished after July 1, 1977 will receive the credit. Users receiving credit for existing facilities are required to provide the Agency with a copy of the demolition permit or other confirmation from the city.”

Monterey One Water, "Residential Capacity Charges", section heading "Demolition Credits" · source document ↗

Every published rate

Every rate below applies to single-family detached.

RateBasisEffectiveAmount
this homeunverified per DU 1 Jul 2024 $6,094

“Charge per Unit FY 24-25 … Billing Unit … Residential … Residential 102/105 107/109 150 1.00 300 300 1.00 1.000 6,056.15 6,093.55 37.40 Each living unit”

Monterey One Water, "Capacity (Impact) Fees for Development", linked by the Agency as "Capacity-Charge-Calculation-PDF"; section heading "Residential"; the column heading standing above 6,093.55 reads verbatim "Charge per Unit FY 24-25", the column to its left "Charge per Unit FY 23-24", the rightmost column "Billing Unit" · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close