The record
“Public Safety – This fee includes the capital facilities fees for the Police and Fire Departments of the City.”
“The fee will fund replacement and expansion of public facilities for Fire and Police department functioning, including a police station, fire department headquarters, and a fire department substation. The fee also will fund capital investments in emergency vehicles and equipment. The updated Public Safety fee covers new development's fair share portion of the total capital investment costs identified by the City, based on service population apportionment.”
“As with current fees in Marina, updated fees would be collected on a citywide basis given the broad scope of capital improvements included in this study.”
2025-10-07
“The foregoing ordinance was introduced at a regular meeting of the City Council of the City of Marina duly held on 16th day of September 2025, and was passed and adopted at a regular meeting duly held on the 7th day of October 2025, by the following roll call vote: AYES: COUNCIL MEMBERS: McAdams, McCarthy, Biala, Visscher, Delgado”
Ordinance No. 2025-15
“The foregoing ordinance was introduced at a regular meeting of the City Council of the City of Marina duly held on 16th day of September 2025, and was passed and adopted at a regular meeting duly held on the 7th day of October 2025, by the following roll call vote: AYES: COUNCIL MEMBERS: McAdams, McCarthy, Biala, Visscher, Delgado”
at building permit
“For new development, mitigation fees shall be charged and payable as set out in Table 1 of this chapter, as set forth in the attached one (1) page, marked Exhibit "A," and incorporated herein by this reference thereto. The director shall determine, based on the type of development, the corresponding fee to be paid pursuant to this chapter. Except as otherwise provided by law or development agreement, the fees shall be paid at the time of issuance of any building permit for new development within the city.”
City of Marina, the agency that levies it
“The City retains all impact fees in a separate Public Facility Impact Fee Fund.”
“The attached ("EXHIBIT A") shows the current and proposed new Development Public Facilities Impact Fees effective January 1, 2026. These fees are applied to all new development unless there is a previously approved Development Agreement.”
“Effective Date. This ordinance shall take effect and be in force sixty (60) days from and after its final passage.”
Every published rate
| Land use | Applies to | Basis | Effective | Amount |
|---|---|---|---|---|
| none | ||||
| Multi-family | none | per KSF (per 1,000 square feet) | — | $3,877 |
the line this rate was read from
the levying document · source document ↗
| ||||
| Senior | none | per KSF (per 1,000 square feet) | — | $3,276 |
the line this rate was read from
the levying document · source document ↗
| ||||
| Senior | none | per KSF (per 1,000 square feet) | — | $1,638 |
the line this rate was read from
the levying document · source document ↗
| ||||
| — | ||||
| Single-family detached | this home | per sq ft | 1 Jan 2026 | $2.01 |