DevFeeFinder
TransportationSet by city fee ordinanceCitation EGMC 16.95

I-5 Subregional Corridor Mitigation Fee

Charged on new development in Elk Grove. Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. Collected at building permit.

What one house pays

$4,306

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot — this fee varies by zone, so see the full schedule below.

Share of Elk Grove's total
5%
Total one-time fees here
$90,015
Adjustment
Adjusts yearly · another named index · July
what the document says

annual

Next expected change
1 Jul 2027 rate on file is stale
!

A scheduled adjustment has passed since this rate took effect

This fee escalates annually. The rate on file is effective 1 Jan 2026, and at least one adjustment has fallen due since. The current amount is probably different, and for an indexed fee almost certainly higher. The next change after that is expected 1 Jul 2027.

The figure is published as held rather than projected forward, because a number computed from an index is not a number quoted from an adopted schedule. It is flagged so you can check the agency's current schedule before relying on it.

The record

Why it exists

“The City of Elk Grove administers several development impact fee programs that fund new development's share of certain capital infrastructure projects.”

City of Elk Grove 2026 Development Related Fees, Last Updated July 1, 2026, p. 15, "DEVELOPMENT IMPACT FEE PROGRAMS" · source document ↗
What it pays for

“I-5 Subregional Corridor Mitigation Fee, which funds Interstate 5 transportation facilities.”

City of Elk Grove 2026 Development Related Fees, Last Updated July 1, 2026, p. 15, item 7 under "CITYWIDE AND REGIONAL DEVELOPMENT IMPACT FEE PROGRAMS" · source document ↗
Where it applies

“City of Elk Grove (District 4)”

City of Elk Grove 2026 Development Related Fees, Last Updated July 1, 2026, p. 24, first header row of the I-5 Subregional Corridor Mitigation Program fee table · source document ↗
When it is paid

at building permit

“These development impact fees are due at the time of building permit issuance and may not be paid prior to permit issuance.”

City of Elk Grove 2026 Development Related Fees, Last Updated July 1, 2026, p. 15 · source document ↗
Who collects it

City of Elk Grove

“There are six citywide and one regional development impact fee programs collected and/or administered by the City of Elk Grove as outlined below.”

City of Elk Grove 2026 Development Related Fees, Last Updated July 1, 2026, p. 15; the I-5 fee is item 7 of that list of seven · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
—
Single-family detached this home per DU 1 Jan 2026 $4,306

“Single-Family (1-2 units) | DU | 1.00 | $ 4,181.07 | $ 125.43 | $ 4,306.50”

City of Elk Grove 2026 Development Related Fees, Last Updated July 1, 2026, p. 24, "I-5 Subregional Corridor Mitigation Program (with Cost per DUE = $4,306.50)", Residential row 1; columns Land Uses / Units / DUE Rate / Base Fee / Admin Fee (3%) / Total · source document ↗
none
Multi-family none per DU — $2,669
the line this rate was read from

“Multi-Family | DU | 0.62 | $ 2,591.33 | $ 77.74 | $ 2,669.07”

the levying document · source document ↗
Senior none per DU — $1,679
the line this rate was read from

“Single-Family Age Restricted | DU | 0.39 | $ 1,630.24 | $ 48.91 | $ 1,679.15”

the levying document · source document ↗
Senior none per DU — $1,378
the line this rate was read from

“Multi-Family Age Restricted | DU | 0.32 | $ 1,338.28 | $ 40.15 | $ 1,378.43”

the levying document · source document ↗
TOD (within 1/2 mile of a transit station)
Multi-family none per DU — $1,980
the line this rate was read from

“Multi-Family TOD | DU | 0.46 | $ 1,922.21 | $ 57.67 | $ 1,979.88”

the levying document · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close