The record
“The Sewer Major Facilities fee pays for the construction and financing of major sewer trunk lines, treatment capacity, and recycled water transmision to serve growth.”
“Debt Service on past capacity upgrades at the Fresno Regional Plant. Debt service on the construction of the City of Clovis treatment plant including the first 2.7 mgd treatment capacity, Pump Station E, Pump Station B, Ashlan Force mains, recycled water pump station and transmission system. Construction and financing costs for future plant expansions. Construction and financing costs for future upgrades and capacity purchases at the Fresno Regional plant. Construction and financing costs for the future construction of Shepherd Avenue force mains and Dewolf trunk mains. Construction and financing costs for the future construction of trunk mains to serve growth in Heritage Grove and the Northeast Village.”
City of Clovis, the agency that levies it
“TO: Mayor and City Council FROM: Finance Department DATE: January 16, 2024 SUBJECT: Finance – Receive and File – Status Report of Development Fee Funds for the fiscal year ended June 30, 2023.”
Every published rate
| Land use | Applies to | Basis | Effective | Amount |
|---|---|---|---|---|
| none | ||||
| Senior | nonethis home | per EDU | — | $9,661 |
the levying document · source document ↗
| ||||
| Multi-family | none | per DU | — | $7,825 |
the line this rate was read from
the levying document · source document ↗
| ||||
| — | ||||
| Single-family detached | this home | per DU | 21 Jul 2025 | $9,661 |
cms2.revize.com · source document ↗
| ||||
| All | Sewer oversize, all areas except RT Ph 1,2 | per acre | 21 Jul 2025 | $1,123 |
the line this rate was read from
cms2.revize.com · source document ↗
| ||||