Public safetySet by county fee ordinanceCitation Placer County Code Art. 15.30; Ord. 4769-B

Placer County Public Facilities Impact Fee

Levied by County of Placer (Placer County Board of Supervisors) on new development in Auburn. Collected at building permit.

What one house pays

$3,668

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Auburn's total
13%
Total one-time fees here
$29,037
Adjustment
Adjusts yearly · consumer price index · October
what the document says

California CPI (DIR, all urban consumers), June to June, annual

Next expected change
1 Oct 2026 due within 3 months

The record

Why it exists

“The purpose of the Public Facilities Impact Fees stems from the County General Plan policies to mitigate the impacts of new development through fair share payment for the construction of a range of public facilities for general administration, jails and public protection, health and human services, public works, agriculture, etc.”

Attachment A, Resolution, October 7, 2025, resolved finding 1, packet p. 379 · source document ↗
What it pays for

“Facilities to be funded under the Fee Program include expansion and construction of office space, libraries, adult and juvenile detention facilities, health and human services space, social service facilities, communications/dispatch equipment, warehouse, animal services facilities, vehicles and related furnishings and equipment.”

Exhibit 1, FY 2024-25 Public Facilities Impact Fee Program Annual Fiscal Report, October 2025, section A "The type of Fee in the accounts or funds", report p. 2 / packet p. 381 · source document ↗
Where it applies

“The PFIF applies to the unincorporated areas of Placer County, and it was subsequently adopted in the cities of Roseville, Rocklin, Lincoln, Auburn, Colfax, and the Town of Loomis.”

Memorandum, County Executive Office Land Use Division, to Honorable Board of Supervisors, October 7, 2025, "BACKGROUND", p. 1 / packet p. 375 · source document ↗
When it was adopted

2002-01-28

“Adoption of the Fee became effective with Fee collection at 100% for residential development by the cities of Rocklin and Roseville in July 2000, the City of Lincoln on April 25, 2001, the Town of Loomis on March 10, 2001, and the City of Auburn on January 28, 2002. Fee collection for non-residential development in each of these cities began at 50% effective January 1, 2002, increasing to 100% effective January 1, 2004.”

Exhibit 1, FY 2024-25 Public Facilities Impact Fee Program Annual Fiscal Report, County Executive Office, October 2025, opening paragraph, report p. 2 / packet p. 381 · source document ↗
Who adopted it

Ordinance No. 4769-B

“The Public Facilities Impact Fee (PFIF) was adopted by Ordinance 4769-B on October 15, 1996, and was first collected in 1997, to mitigate impacts of new development on County facilities.”

County Executive Office / Land Use Division memorandum to the Board of Supervisors, "Public Hearing / FY 2024-25 Public Facilities Impact Fee Annual Fiscal Report and Inflationary Adjustment", October 7, 2025, BACKGROUND, packet p. 375 · source document ↗
When it is paid

at building permit

“The following building fees will be paid at the time of permit issuance: Building Permit Fee: Based on the fee table on the total evaluation, SMIP (.00013 of valuation), SB1473 ($1/$25,000 of valuation), For new units, sewer connection fee (typically $8615), Facilities and Equipment fee ($2,750), and Placer County facilities fee ($3,560.93.).”

City of Auburn Building Department, "RESIDENTIAL BUILDING PERMIT", Rev. 12-2024, item 8 · source document ↗
Who collects it

City of Auburn — Building Department

“Collecting agencies levy a charge of 2.5% for administration of the Public Facilities Impact Fee Program. This amount offsets the cost for collection of the Fee, accounting for and reporting the collections to the County, and administrative duties.”

Exhibit 1, FY 2024-25 Annual Fiscal Report, October 2025, section M "Review of administrative charge", report p. 7 / packet p. 386 · source document ↗
Credits and offsets

“In FY 2024-25, there were no refunds made pursuant to Section 66001 subdivisions (e) and (f).”

Exhibit 1, Annual Fiscal Report, October 2025, section H, report p. 6 / packet p. 385 · source document ↗
How it changes

“The County Fee was implemented at 50% beginning on February 1, 1997, and at 100% effective January 1, 1998. Adoption of the Fee became effective with Fee collection at 100% for residential development by the cities of Rocklin and Roseville in July 2000, the City of Lincoln on April 25, 2001, the Town of Loomis on March 10, 2001, and the City of Auburn on January 28, 2002. Fee collection for non-residential development in each of these cities began at 50% effective January 1, 2002, increasing to 100% effective January 1, 2004.”

Exhibit 1, Annual Fiscal Report, October 2025, opening paragraph, report p. 2 / packet p. 381 · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
—
Single-family detached this home per DU 8 Dec 2025 $3,668

“Table 1 | Placer County Public Facilities Impact Fee Schedule | Effective December 8, 2025 — Land Use Categories row 'Single Family Dwelling', column 'Auburn and Rocklin (Cities with County Libraries)', sub-column 'Base Fee': $3,667.75”

Exhibit 1, FY 2024-25 Annual Fiscal Report, October 2025, section B "Amount of the Fee", Table 1, report p. 3 / packet p. 382 · source document ↗
Auburn and Rocklin (Cities with County Libraries)
Senior Age Restricted Sr Citizens per DU — $2,411
the line this rate was read from

“Table 1 | Placer County Public Facilities Impact Fee Schedule | Effective December 8, 2025 — row 'Age Restricted Sr Citizens', column 'Auburn and Rocklin (Cities with County Libraries)', sub-column 'Base Fee': $2,411.46”

the levying document · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close